The Cascades Hotel will undergo a refurbishment that is planned from the 18th of June until the 31st of October 2013. The sections of the Hotel that will be affected include The Vista Bar, Porte Cache, Hotel Entrance, Reception area, Lobby and the Public Toilets.

Scheduled demolishing work will to take place from 11h00 to 15h00 on Mondays to Fridays so as not to discomfort our guests.

The following sections will be affected:

  • Old Scalini area 18-Jun 21-Aug
  • The Vista Bar 18-Jun 21-Aug
  • Rooms 321 & 322 18-Jun 21-Aug
  • Current Kitchen 18-Jun 21-Aug
  • The Porte Cochacre 08-Jul 21-Aug
  • Hotel Entrance 22-Jul 12-Aug
  • Lift Landing 22-Jul 03-Sep
  • Front Office 23-Aug 17-Oct
  • Hotel Front area 12-Aug 03-Sep
  • Public Toilets 19-Aug 30-Sep
  • Old Reception Revamp 03-Sep 28-Oct
  • Hotel Lobby 03-Sep 28-Oct